Installation waste from a 60 seat dining area runs to about 8 cubic metres of cardboard and timber packing.
Open21 September 2026
Phased installation is normal on a live site, and the cost is protection instead of labour.
Furniture installed in week one and covered until week six takes more damage from the covering than from use. Phasing follows the trades instead of the delivery schedule, and a run split across two deliveries needs both halves from the same dye lot. Dining area installed before the floor is finished will be moved, and the second move is where corners break.
Split run needs one batch, which is a material reservation made at the order instead of a change on site.
Floor level decides how a run looks. The 25 mm fall across 6 m shows as a gap under one end, and the feet inside the plinth take 15 mm of it before anybody notices. Anchoring is part of the furniture specification. Drywall takes a different fixing from brick, and a run that relies on the wrong one moves the first time somebody leans on it.
Phasing is normal on a live site. Installing half the floor early means protecting it for weeks, and protection costs less than a second delivery. Getting a 2,400 mm run round a 90 degree corner on a 1,100 mm stair is arithmetic. The numbers either clear or they fail, and the stair does not argue. Measure the diagonal before the order is cut.
Protection on a live site is part of the furniture method. Corner guards and felt pads cost a fraction of the first replaced panel, and cartons stay on until the piece is in position. Photograph the dining area before the install starts. Damage found afterwards is a dispute that one date-stamped photograph prevents, and the photograph costs nothing to take.
Leave the survey drawing with the building dimensions on it. The next person to work in the dining area needs the drawing. The order number says nothing about where the piece goes. Power and light come from the site, and the furniture method says what it needs. One socket for a drill and 300 lux to see a joint is the minimum, and it belongs in the method statement instead of in a call on the day.
Cartons come off in the order the pieces go in. Every piece stays wrapped until it is lifted into position, because a carton taken off early is a piece that gets moved twice. Our steakhouse furniture covers every model, size and finish.
Cutting on site is a decision made at the factory. Every joint cut in the dining room leaves a film on every cover. That is why the run arrives with the scribe allowance already on it.
Cleaning at the end of the install is part of the install. The furniture crew wipes the dust it made, and the handover is not finished until the covers are clean. The final walk happens 48 hours before opening. On the morning there is no time left to fix what the walk turns up. Two days is enough to replace a part and not enough to re-plan a run, which is what makes it the right deadline. Who makes the frames is set out on the factory profile.
After the floor and after the wall finish, because both trades need the wall a booth sits against. The date is set backwards from the opening.
Installation waste from a 60 seat dining area runs to about 8 cubic metres of cardboard and timber packing.
OpenTouch-up on site covers chips in a coating, scuffs on a cover and marks on a timber edge.
OpenMissing hardware is a packing claim, proved by the carton instead of by the dining area.
OpenDoors, stairs, floors, anchoring and the sequence that keeps an opening date.
OpenDimensions, seat count and the finish you have in mind are enough to start. What comes back is a quantity per line, a leather card, a sample date and a loading window. All of it fits on one page.