Spares on site
Spare parts on site cover the failures that happen in year one: glides, a cover or two and a hardware set.
Open27 October 2026
Fixing heights come off the furniture drawing instead of off the wall.
Booth back fixing sits on the centre line of a 520 mm back, the table bracket follows a 750 mm top and anything hung above a run clears the back by 200 mm. Those numbers go to site before the wall is finished, so the fixing lands where the drawing says instead of 30 mm out. Booth back fixing 30 mm low moves the run and closes the gap at one end of a shelf-length run.
Wall brackets for banquette tables are set from the finished floor and the finished top, which are different numbers.
Stairs are the constraint that gets discovered late. The 1,100 mm stair with a turn sets the maximum length of every piece that goes upstairs, and that length is shorter than the drawing assumes. Floor level decides how a run looks. The 25 mm fall across 6 m shows as a gap under one end, and the feet inside the plinth take 15 mm of it before anybody notices.
Anchoring is part of the furniture specification. Drywall takes a different fixing from brick, and a run that relies on the wrong one moves the first time somebody leans on it. Sequence matters: bases, then tops, then backs, then covers on site where the cover is a separate item. Doing it the other way means moving finished pieces twice.
The scribe line is furniture work. The 30 mm filler panel cut at the factory covers the gap that a scribed back would leave visible. Fixing to a stud wall needs a pattress behind the board or a counterweighted base. The choice depends on whether the run can move, and the factory draws the fixing either way.
Level and plumb are different tolerances, and a booth touches both. The floor that is level with a wall 15 mm out of plumb leaves a gap at the top that a filler panel has to close. Site access needs names before it needs tools. The crew that turns up without passes spends the first morning at the gate, and that morning is in the programme. Sizes, finishes and lead times are set out across steakhouse seating.
Laser levels pay for themselves on a booth run. The run set out to a line 6 m long stays true. The run set out from one corner and a tape drifts 8 mm by the far end. Anchor points are drilled to the furniture drawing.
The fitter's judgement changes from day to day. Socket 40 mm below the fixing line is the case the drawing exists to catch, and missing it costs a delay instead of a repair.
Cleaning at the end of the install is part of the install. The furniture crew wipes the dust it made, and the handover is not finished until the covers are clean. The final walk happens 48 hours before opening. On the morning there is no time left to fix what the walk turns up. Two days is enough to replace a part and not enough to re-plan a run, which is what makes it the right deadline. Who makes the frames is set out on the factory profile.
Then the fixing is found instead of set, which means a stud finder and possibly a resin anchor. Both are slower and neither is as strong as a fixing into a stud.
Spare parts on site cover the failures that happen in year one: glides, a cover or two and a hardware set.
OpenAs-built drawing records the dining area with the furniture in place, instead of the furniture on a drawing.
OpenClaims refused after installation are usually refused on causation instead of on damage.
OpenDoors, stairs, floors, anchoring and the sequence that keeps an opening date.
OpenDimensions, seat count and the finish you have in mind are enough to start. What comes back is a quantity per line, a leather card, a sample date and a loading window. All of it fits on one page.
Own workshop · EXW Foshan or DDP
Send the plan and the seat count. Answer inside two working days.
Chat on WhatsApp