Steakhouse furniture site survey records five numbers: the wall length at three heights, the floor-to-window height, the clear door width, the narrowest point on the route and the floor level along the run.
Nothing else changes a drawing. Survey work taken from a plan is survey work on the plan, and the two numbers that most often differ are the wall length and the floor level. Wall length is taken at three heights, because a wall that reads 4,200 mm at the skirting is often 4,215 mm at the datum and a run follows the widest point.
The route is part of the survey: a 900 mm door and a 750 mm service corridor make a 750 mm order.
Lift size matters as much as door width. The 1,200 by 1,500 mm car takes a 2,000 mm run on the diagonal and nothing longer. Delivery stops where the route stops. The survey should record the narrowest point between the truck and the dining floor, which is often a service corridor rather than the front door.
Fixing heights come off the furniture drawing. The finished wall moves, and the drawing does not. Fixed 30 mm low, the run closes the seat gap at one end and no shim moves it back. Protection on a live site is part of the furniture method. Corner guards and felt pads cost a fraction of the first replaced panel, and cartons stay on until the piece is in position.
The wall decides the run. The dining area that cannot take a 2.4 m run gets a spliced run, and the splice belongs in the drawing instead of on site. Level and plumb are different tolerances, and a booth touches both. The floor that is level with a wall 15 mm out of plumb leaves a gap at the top that a filler panel has to close.
Leave the survey drawing with the building dimensions on it. The next person to work in the dining area needs the drawing. The order number says nothing about where the piece goes. The unloading point is a decision made before the truck arrives. The 20 m carry through a finished dining room takes four people and a day. The same goods dropped at the service door take two and an hour. Our steakhouse furniture covers every model, size and finish.
Lifts need booking and a lined car. Plywood on the floor and the walls before the first run goes up saves the door frame and the run, and it takes twenty minutes a lift. Goods lifts are smaller than passenger lifts. The 1,400 mm car that takes a 2,400 mm run on the diagonal is often the only route upstairs, and its size belongs in the survey.
Cartons come off in the order the pieces go in. Every piece stays wrapped until it is lifted into position, because a carton taken off early is a piece that gets moved twice. Two people fit about 25 covers a day on loose furniture and 12 metres of booth run. Those are the numbers that turn an install into a programme instead of a hope. Who makes the frames is set out on the factory profile.
The factory or its installer, before cutting. Survey work by the site contractor records the building, which is useful and is not a furniture survey.
Installation method statement for furniture runs to one page: access, sequence, fixings, protection and who signs off.
OpenSite contact protocol for a furniture delivery gives the crew a drawing, a sequence and a named person on site.
OpenColour mismatch needs a physical sample and a lot number.
OpenDoors, stairs, floors, anchoring and the sequence that keeps an opening date.
OpenDimensions, seat count and the finish you have in mind are enough to start. What comes back is a quantity per line, a leather card, a sample date and a loading window. All of it fits on one page.
Own workshop · EXW Foshan or DDP
Send the plan and the seat count. Answer inside two working days.
Chat on WhatsApp