Ember & Chair Steakhouse seating · Foshan, China WhatsApp
Send the floor plan and the seat count. Layout and quote back in two working days. Talk to us →
Steakhouse furniture Ember & ChairSteakhouse seating 829 models Design
Home/Blog/Holidays

Two to three weeks of production disappear around a national holiday.

Factory holiday schedule affects a project more than a shipping delay, because production stops and does not catch up.

Shutdown
about two weeks
Effective
longer, travel time
Effect on 35 days
40 percent of the window

What a factory can promise

The two week shutdown in a 35 day lead time removes 40 percent of the window. Orders that straddle a holiday should be scheduled to finish before it rather than after. Workers travelling home take longer to return than the official holiday, so the effective shutdown is longer than the calendar shows.

The shipment that would have sailed during a shutdown slips by a full month, because the container booking also moves.

Where orders go wrong

Lead time runs 25 to 35 days from the approved sample. The seven to ten days inside that is sampling, and it is the part that gets forgotten in a schedule. Capacity is a calendar. Ask which week the line is booked. Monthly capacity is what the workshop can do, and the booking is when it will do yours.

Written change control is the difference between a variation and an argument. Every change after cutting should have a date, a cost and a signature. The calendar has two bottlenecks: sampling and coating. Cutting and assembly absorb change. The colour batch does not.

What to agree in writing

Orders placed before a national holiday lose two to three weeks of effective production, and that has to be in the schedule instead of in an apology. Shipping schedules are not production schedules. The container that sails on the 14th has to be packed by the 10th, which means the last process has to finish by the 8th.

Insurance and title transfer are commercial terms that get ignored until a container is lost. Agree them before the first shipment. Agreeing them afterwards means a re-make. Payment terms follow the schedule. Thirty percent on order and the balance against the bill of lading copy is standard. The balance paid before production starts is a loan to the factory with no security. Every model sits inside the steakhouse range.

What it costs at year five

Sampling takes seven to ten working days and the freight is usually on the buyer. Building the sample into the lead time at the quotation stage is what stops the first order arriving late. Factory audits are worth a day when they look at three places: the cutting table, the upholstery bench and the packing area. The showroom says nothing that the packing area does not contradict.

Currency matters on anything over sixty days. The quote in dollars against costs in renminbi moves three percent on a bad month, and the clause that reopens the price past that point protects both sides. Ask for the packing list and three photographs a week before the vessel sails. At that point a missing model can still be made. After the container is closed it is a claim. The workshop floor is described on our workshop.

One more question

Can production run through a holiday?

Partially, at extra cost, and only for processes that do not depend on labour. Cutting and upholstery stop.

Peak season

Furniture production peaks in the weeks before the northern spring and autumn openings, when most dining areas are finishing.

Open

Lead time

Furniture lead time of 25 to 35 days runs from the approved sample instead of from the payment.

Open

Armed chairs

Armchair width runs 560 to 620 mm against 480 mm for the same chair without arms.

Open

Sourcing and terms

MOQ, samples, quotations, payment, audits and what a factory can actually promise.

Open

Send the floor plan. Get the layout and the quote.

Dimensions, seat count and the finish you have in mind are enough to start. What comes back is a quantity per line, a leather card, a sample date and a loading window. All of it fits on one page.

Own workshop · EXW Foshan or DDP

Design referencesFourteen positions, measured→ Buying guidesEight decisions, with the numbers→ BlogThree hundred notes, two a day→ Project filesThree projects, and what changed→ The spec sheetNine numbers and the tolerance→ Talk about your steakhouseSend the plan, get a seat count→