Ember & Chair Steakhouse seating · Foshan, China WhatsApp
Send the floor plan and the seat count. Layout and quote back in two working days. Talk to us →
Steakhouse furniture Ember & ChairSteakhouse seating 829 models Design
Home/Blog/Lead time

Twenty five to thirty five days, counted from the approved sample.

Furniture lead time of 25 to 35 days runs from the approved sample rather than from the payment, and the 7 to 10 days of sampling sits inside that window.

Lead time
25 to 35 days
From
approved sample
Sampling inside
7 to 10 days

Capacity and calendar

The schedule that counts from the deposit and assumes the sample is instantaneous is a schedule that is a week short before it starts. Coating is the second bottleneck after sampling, because a colour batch does not absorb a change the way cutting does. The repeat order is faster because the sample, the drawing and the colour already exist, which is a real advantage worth planning.

Sample cost is credited against the order, which means it is a commitment device instead of a charge. Buyers who never order pay for the workshop time. Buyers who do, do not. Third party inspection is worth the fee on a first order and rarely worth it on a repeat.

The first order is where the assumptions differ. The repeat is where they have already been tested.

The delays that repeat

Deposits are schedule commitments on both sides. Once it clears, the sample date is fixed and the delivery window starts, so the sequence matters more than the percentage. What changes mid-order is usually the cover or the quantity. Both ripple through material ordering, and both have a point past which the change costs more than it saves.

Documents that protect both sides are short: a drawing, a specification, a sample reference, a schedule and a change procedure. Anything longer is usually unread. Payment terms follow the schedule. Thirty percent on order and the balance against the bill of lading copy is standard. The balance paid before production starts is a loan to the factory with no security.

What to confirm before paying

The production clock starts at the approved sample and the cleared deposit, whichever is later. The order that clears on a Friday and approves the sample three weeks later is three weeks behind before a saw is switched on. Sampling takes seven to ten working days and the freight is usually on the buyer. Building the sample into the lead time at the quotation stage is what stops the first order arriving late. Sizes, finishes and lead times are set out across steakhouse seating.

What the sample should prove

Change control starts at cutting. Anything changed after the hide is cut costs the material as well as the labour, and that is a clause worth reading before the first amendment. The contract needs three attachments. One attachment leaves the other two open to argument. The drawing, the approved colour card and the packing list are the documents a dispute actually turns on, and the purchase order text is not one of them.

Drawings go back to the factory with comments within forty eight hours or they are approved by default. That deadline is worth writing down, because the chair built to a drawing nobody read is still a chair. Reorders should reuse the drawing, the colour card and the packing list from the first order. Starting a reorder from a conversation is how the second batch comes back 40 mm narrower than the first. The workshop floor is described on our workshop.

One more question

Why does a repeat order arrive faster?

Because nothing has to be approved twice. The saving is the sampling window, which is about a week.

Volume

Furniture volume discount is not linear, because the cost structure changes with quantity.

Open

Chair price

Price per steakhouse chair spans a factor of three between a powder coated steel frame with a PU seat and a solid beech frame with a full grain hide cover.

Open

Tenon size

Tenon length at two thirds of the rail width keeps a joint from tearing out the leg.

Open

Sourcing and terms

MOQ, samples, quotations, payment, audits and what a factory can actually promise.

Open

Send the floor plan. Get the layout and the quote.

Dimensions, seat count and the finish you have in mind are enough to start. What comes back is a quantity per line, a leather card, a sample date and a loading window. All of it fits on one page.

Own workshop · EXW Foshan or DDP

Design referencesFourteen positions, measured→ Buying guidesEight decisions, with the numbers→ BlogThree hundred notes, two a day→ Project filesThree projects, and what changed→ The spec sheetNine numbers and the tolerance→ Talk about your steakhouseSend the plan, get a seat count→