Booth assembly sequence runs bases, tops, backs, then covers where the cover is a separate item.
Working the other way means moving finished pieces twice, and a run that weighs about 90 kg a metre does not enjoy being moved. On a fixed run the back fixing comes before the seat deck, because the deck blocks access to the bracket. Tops go on after the bases are levelled, because levelling under a top means lifting it twice.
Backs that fit over a deck go last and backs that fit behind it go first. That is why the drawing shows which.
Floor level decides how a run looks. The 25 mm fall across 6 m shows as a gap under one end, and the feet inside the plinth take 15 mm of it before anybody notices. Fixing heights come off the furniture drawing. The finished wall moves, and the drawing does not. Fixed 30 mm low, the run closes the seat gap at one end and no shim moves it back.
Levelling is done before anchoring, never after. Runs anchored level to an unlevel floor hold the frame in a twist that shows at every joint. What goes wrong on the day is almost always access. Pieces that fit the dining area but not the lift go back on the truck.
Fixing to a stud wall needs a pattress behind the board or a counterweighted base. The choice depends on whether the run can move, and the factory draws the fixing either way. The handover file should carry the assembly sequence, the fixing specification and the touch-up colour codes. Those three are what a maintenance team asks for first.
Lifts need booking and a lined car. Plywood on the floor and the walls before the first run goes up saves the door frame and the run, and it takes twenty minutes a lift.
Other trades work at the same time as the install. Booth runs fitted before the wall finish take a dust coat on the hide that no cleaning schedule removes. That is why furniture goes last.
Cartons come off in the order the pieces go in. Every piece stays wrapped until it is lifted into position, because a carton taken off early is a piece that gets moved twice. All 829 models are listed on the steakhouse furniture page.
Cutting on site is a decision made at the factory. Every joint cut in the dining room leaves a film on every cover. That is why the run arrives with the scribe allowance already on it.
Two people fit about 25 covers a day on loose furniture and 12 metres of booth run. Those are the numbers that turn an install into a programme rather than a hope. The final walk happens 48 hours before opening. On the morning there is no time left to fix what the walk turns up. Two days is enough to replace a part and not enough to re-plan a run, which is what makes it the right deadline. Who makes the frames is set out on the factory profile.
Because a booth run is heavy and fixed. Any piece that has to come out again takes two people and marks the finish at the fixing.
Furniture assembly tools for a booth install run to a cordless driver with the correct bit, a rubber mallet, a level, a tape, a knife and the hex keys matched to the hardware.
OpenFloor protection during installation belongs to whoever is on site.
OpenBooth seats can hinge to give storage under the deck, which is useful in a dining area with no back of house and adds about 25 mm to the seat height.
OpenDoors, stairs, floors, anchoring and the sequence that keeps an opening date.
OpenDimensions, seat count and the finish you have in mind are enough to start. What comes back is a quantity per line, a leather card, a sample date and a loading window. All of it fits on one page.
Own workshop · EXW Foshan or DDP
Send the plan and the seat count. Answer inside two working days.
Chat on WhatsApp