Floor protection
Floor protection during installation belongs to whoever is on site.
Open29 July 2026
Furniture assembly tools for a booth install run to a cordless driver with the correct bit, a rubber mallet, a level, a tape, a knife and the hex keys matched to the hardware.
Kits that arrive bagged per run mean one bag per row rather than a box to sort. The bit is the item that stops a job, because a run uses one fastener size and a crew with the wrong bit cannot start. Impact driver on a thread insert strips the insert, so the clutch setting matters more than the torque.
Spare glides and two covers travel with the kit, because those are the parts replaced in year one.
Door width decides what can arrive assembled. Below 900 mm clear, booth runs travel knocked down and the assembly hours go into the install programme. Lift size matters as much as door width. The 1,200 by 1,500 mm car takes a 2,000 mm run on the diagonal and nothing longer.
Anchoring is part of the furniture specification. Drywall takes a different fixing from brick, and a run that relies on the wrong one moves the first time somebody leans on it. The crew needs a drawing, a sequence and a named contact. Without all three, the first question stops the job for an hour.
Sequence matters: bases, then tops, then backs, then covers on site where the cover is a separate item. Doing it the other way means moving finished pieces twice. The wall decides the run. The dining area that cannot take a 2.4 m run gets a spliced run, and the splice belongs in the drawing instead of on site.
Other trades work at the same time as the install. Booth runs fitted before the wall finish take a dust coat on the hide that no cleaning schedule removes. That is why furniture goes last.
Temporary lighting tells the truth about colour. The dining area lit at 2700 K during the install and 3500 K at opening shows two different covers, and neither is wrong. Two people fit about 25 covers a day on loose furniture and 12 metres of booth run. Those are the numbers that turn an install into a programme instead of a hope. Sizes, finishes and lead times are set out across steakhouse seating.
Laser levels pay for themselves on a booth run. The run set out to a line 6 m long stays true. The run set out from one corner and a tape drifts 8 mm by the far end. Cleaning at the end of the install is part of the install. The furniture crew wipes the dust it made, and the handover is not finished until the covers are clean.
Handover includes the spare parts, the touch-in kit and the assembly drawings. The dining area without them is a dining area that calls the factory for a 2 dollar glide in year two. Who makes the frames is set out on the factory profile.
It should send the bits, the hex keys and the glides, because all three are specific to the hardware. The rest is standard site kit.
Floor protection during installation belongs to whoever is on site.
OpenStair carry limits the length of any piece that goes upstairs.
OpenDining chair width runs 450 to 520 mm at the seat, and 480 mm is the number that lets two chairs sit side by side at a 1,400 mm table without touching.
OpenDoors, stairs, floors, anchoring and the sequence that keeps an opening date.
OpenDimensions, seat count and the finish you have in mind are enough to start. What comes back is a quantity per line, a leather card, a sample date and a loading window. All of it fits on one page.
Own workshop · EXW Foshan or DDP
Send the plan and the seat count. Answer inside two working days.
Chat on WhatsApp